Been to view a job today which I’m fitting spacia tiles in next week. Originally two rooms, the builders have dropped the wall and put a steel in marking it one room. It’s asphalt in both sides up to the wall that’s been removed. I’ve got a 20mm height difference between the two. I’ll post some pictures. How’s best to go about prepping it. I was going to uplift the higher side which would bring the original concrete slab flush with asphalt. Screed the concrete because it’s really rough,Dpm and then screed over the whole floor.
cheers daz Also there is a channel we’re the concrete block was it’s now slightly lower than the asphalt and there’s is vis queen over the bottom course. Can I just screed over this?
That must take a life time to dry 110 is 20 hours to dry at 3mm and an extra 20 hours per mm after that I sh×$ you not