Right lads got a job where I need to use a dpm and it needs to set fast so I can screed over with a fast dry screed. In your opinion what's the quickest one to dry. Usually I will use either ardex 1c or rapid and go and come back next day to fit or latex . However this job requires me to do a sandwich and the window is 10 hours before traffic comes rushing in. Any thoughts
Concrete rough so I plan on latex then dpm , but need to latex again to protect dpm before foot traffic. I planned on using altro solo uni fast track , get some heating and blowers going on and hope for best. Just wondered if anyone had done this before.
It won't work Dpm dries through a chemical reaction & you need to make sure the laxtex is completely dry before you Dpm it not just walk on hard or you'll have problems
I know first coat will be dry. Its the next night I need to get a dpm down then latex over it to protect it
I've been informed by Uzin that their moisture control can be used on no existing Dpm. Sets in couple hrs
I had to get a 40m2 kitchen fully prepped early this week and I did the same. managed to latex (level it 2 ultra floor) at 7am, F77 down at 1:30pm, top coat screed at 5pm, cleaned up, crap out and loaded and out the door for 6.30pm. I was surprised how quick that Level it screed was drying, love the stuff now! I love my new itools mixing station
I like uzin's system, where the Dpm is part of the screed. So no messing & get it down in 1 hit after you've primed the floor. #wellquick