    Arrived on site today, and found some huge, day joints

    20190701_085836.jpg

    The finish in this area is to be 2mm safety. So how would you treat this ?
     
  2. Spacey

    Spacey Super Moderator Staff Member

    6,503
    1,881
    113
    Needs metal stitches and resin
     
  3. Neilydun

    Neilydun Well-Known Member

    2,893
    1,227
    113
    Never seen that done. Is that re-bar and resin ?
     
  4. Spacey

    Spacey Super Moderator Staff Member

    6,503
    1,881
    113
  5. merit

    merit Well-Known Member

    8,222
    1,681
    113
    One of my customers did that after their builder bodged the screed. Worked a treat


    Sent from my iPhone using Tapatalk
     
  6. Distinctive Adam

    Distinctive Adam Well-Known Member

    1,726
    503
    113
    Sorry, not sorry
     

    Attached Files:

  7. Glenn H

    Glenn H Well-Known Member

    645
    140
    43
    You could also look and adding a reinforcement webbing over the top after the above process just to add extra piece of mind Neil
     
  8. pf flooring

    pf flooring Well-Known Member

    1,600
    602
    113
    Epoxy the joint? Lazy from builders as per everytime, slurry the dry edge and it will bond (or should)
     