Prepping a cavity before screed

Discussion in 'Subfloor Preparation' started by Hynesy, Jun 29, 2023.

  1. Hynesy

    Hynesy New Member

    1
    0
    1
    Hi guys

    I have attached pic below. Customer has a window knocked into double doors leaving internal skin of brick and empty cavity, floor is asphalt on concrete which will be screeded with tilemaster trade flow dpm sandwich, how would you prep the cavity in order to bring it upto the asphalt level ready for screed?

    Many thanks
     

    Attached Files:

  2. J d clarkson flooring

    J d clarkson flooring Well-Known Member

    259
    52
    28
    Speak to tile master but possibly fill with there rapid repair mortar
     
  3. merit

    merit Well-Known Member

    8,208
    1,676
    113
    Yeah they have a rapid repair that’s moisture tolerant. Just have to pack out the cavity with insulation. Or if it’s not deep enough take out a row of bricks. Dpm sheet and deep fill/rapid
     
  4. HC&F

    HC&F Well-Known Member

    295
    45
    28
    Ardex a46
     