Quickest way to fit 200 sheets of ply?

Discussion in 'General Flooring Chat' started by tgflooring, Dec 14, 2013.

  1. tgflooring

    tgflooring Active Member

    35
    10
    8
    Hi everyone,

    Got a job starting in the new year.... 600m2 of karndean/Amtico
    The only snag is the subfloor is concrete and customer wants 9mm ply
    to achieve levels for CAT trims. Screed is out the question for some perculiar
    reason!!!

    My question is: How would you do it?

    Done a lot of this before, but not this amount in one area.
    Is it just a case of get on with it, drill, plug & screw
    or is there something out there which can make it any
    quicker?
     
  2. ronbaldo

    ronbaldo Well-Known Member

    258
    35
    28
    Get a heap of labourers lol. Or do a usain BOLT! Fair size of job
     
  3. show flooring

    show flooring Active Member

    33
    7
    0
    Have a look at the gekko gun not used it but seen a demo might speed things up a bit
     
  4. coolevilangel

    coolevilangel Well-Known Member

    4,299
    912
    113
    why is the customer telling you how to do the job???
    wrong way round fella lol
     
  5. Jambo

    Jambo Well-Known Member

    613
    348
    63
    As Mike just said, you're the guy that should be telling them exactly how it should be done. Why would you want to introduce moisture into a 600m2 job when you have the perfect option with screed. Also, the customer will have much less labour to pay for with screed than drilling and screwing plywood.
     
  6. tgflooring

    tgflooring Active Member

    35
    10
    8
    Tried & tested methods to achieve the best finish to the
    trim.
    Like I said before... Done a lot of these in the past.
    150 Lin of trim to pick out walk ways and other areas.
    Screeded some in past but client prefers the finish
    the ply gives.
     
  7. merit

    merit Well-Known Member

    8,208
    1,676
    113
    Could you stick down the ply with a flexable wood adhesive? Need a big notch trowel and have to weight the boards down
     
  8. Spacey

    Spacey Super Moderator Staff Member

    6,503
    1,881
    113
    No chance you'd get me doing that ?

    I'd screed it every time
     
  9. merit

    merit Well-Known Member

    8,208
    1,676
    113
    Bet you would
     
  10. pf flooring

    pf flooring Well-Known Member

    1,600
    602
    113
    Why cant you get it done with a pump? hire one out or sub it to a firm who pump screed, screed for crete ply for wood, id never ply out over crete fullstop.
     
  11. Spacey

    Spacey Super Moderator Staff Member

    6,503
    1,881
    113
    Bet you I wouldn't ?
     
  12. merit

    merit Well-Known Member

    8,208
    1,676
    113
    No different to sticking engineered to concrete!
     
  13. dazlight

    dazlight Super Moderator

    7,203
    1,704
    113
    If floor is flat stick the ply with F3 that would be quick.
     
  14. UVcure

    UVcure Well-Known Member

    481
    338
    63
    Yes done that before with a real big notch and if it's a good screed, concrete nails to hold it until it dries,
     
  15. dazlight

    dazlight Super Moderator

    7,203
    1,704
    113
    Did it about 20 years ago in a class room. Not sure why but we rolled it with the roller. It did stick though.
     
  16. Trimmer

    Trimmer Well-Known Member

    1,464
    490
    83
    Same here. Did a hallway in davinci years ago for shop owner. Height difference so used ply on f3 (with pins to hold till set). Floors still solid
     
  17. dazlight

    dazlight Super Moderator

    7,203
    1,704
    113
    Always been told never to put ply on concrete. But why?
    If the concrete is dry and you drill,plug and glue it, what's the problem?
    The builders I do wet rooms for do that every time for the past 15 years.
    Then again that's only one sheet.
     
  18. coolevilangel

    coolevilangel Well-Known Member

    4,299
    912
    113
    When you have to rip up an old ply'd floor on concrete, have you ever come across one that wasnt rotten to the core?:D
     
  19. Trimmer

    Trimmer Well-Known Member

    1,464
    490
    83
    Do a moisture test. Same as if fitting wood - if its dry enough for wood then ply can go down.

    On a big area though, I'd rather screed
     
  20. tgflooring

    tgflooring Active Member

    35
    10
    8
    I've done a moisture test a couple of weeks ago and it's
    good to go.
    I don't mind doing both, but plying is just very labour intensive.
    Just picking brains to see if there's any quicker way.
     