Well today I went to do what I was told would be a nice little 15m2 Karndean job (only uplift and screed today) well I ripped the carpet up to find old 1" quarry's and after some digging and yes digging I discover it was on an ash bed that was on an earth floor!!!! So my day today was to dig it out ready for the concrete tomorrow, I think this job will be a while until I actually fit it! Could have been worse my mate on the other site is on day 8 of a 550m2 herringbone job that is layed out in a spiders web design. Roll on the end of the school holidays when I can breath again!
That sounds like that would be pretty impressive to behold, reckon you could get pics of the finished job from your mate?
I've had a couple like that. Annoying if it's just a small job and you had planned to hit it out in one day with Fasttrack 30.