Laying lvt directly onto dpm

Discussion in 'Introduce yourself' started by Tim., Mar 20, 2024.

  1. Tim.

    Tim. Member

    5
    0
    1
    Hi,
    I have latexed 20mm flexable screed over electric ufh which was set onto a decoupling membrane. Its going to take a while to fully dry but here is my question. Could I dpm it with a resin based dpm wait for it to dry then lay lvt directly to the dpm? If so which dpm would work for this? I will obviously make sure r/h levels are correct first etc.

    Thanks in advance

    Tim
     
  2. dazlight

    dazlight Super Moderator

    6,865
    1,620
    113
    Should of done the Dpm under the decoupling boards
    Why do you want it above ? What’s compound did you use over the wires ?
     
  3. Tim.

    Tim. Member

    5
    0
    1
    It's not a damp issue other than the latex itself isnt dry and the kitchen is being fitted on Friday.
     
  4. Tim.

    Tim. Member

    5
    0
    1
    It's not a damp issue other than the latex itself isnt dry and the kitchen is being fitted on Friday.
     
  5. Tim.

    Tim. Member

    5
    0
    1
    It's uzin nc196
     
  6. dazlight

    dazlight Super Moderator

    6,865
    1,620
    113
    It will be fine by Friday mate. Also you can’t put a liquid Dpm over a water mix compound as it isn’t moisture tolerant.
     
  7. Rugmunching

    Rugmunching Well-Known Member

    3,679
    630
    113
    You'll be fine, leave it.
    Let them do they're bits, feather patch if need be then fit
     
  8. Tim.

    Tim. Member

    5
    0
    1
    I didn't know that! No dpms at all will go over water based screed?
     
  9. dazlight

    dazlight Super Moderator

    6,865
    1,620
    113
    Most. There are a few I’ve heard. But in most cases you can only go over a latex type.
     